Project Duration
Stipulated Date of Commencement
April 25 2019
Stipulated Date of Completion /
Likely Date of Completion May 24 2019
Likely Date of Completion May 24 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,589,487.48
Project highlights
repairs/upgradation of Government Schools in the State of Goa.
Contractors
M/s. Deepak Marathe
Consultants
M/s Vaishali pednekar (PMC)