Project Duration
Stipulated Date of Commencement
January 16 2019
Stipulated Date of Completion /
Likely Date of Completion January 30 2020
Likely Date of Completion January 30 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,461,292.00
Awarded for
₹ 13,923,377.44
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Rahul Constructions
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repairs/Upgradation and maintenance of Government Schools in the state of Goa- Civil Plumbing and Electrical works:-Bicholim Taluka – Package K ( G.P.S Vathadev – Sarvan , G.P.S. Paltadwada, G.P.S. Naigini – Kudchire and G.P.S Kholpewadi – Sal )
View Project
Repairs/Ugradation & Maintenance of Government Schools in the Sate of Goa – Bardez Taluka -GPS Bamburdem Moira, GPS St. Cruz Bastora.
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka: Package-E (GPS Mhalshekarwada Parye, GPS Dhatwada Padoshe, GPS Rawan, GPS Gaonkarwada Honda, GHS Bhuipal)
View Project