Project Duration
Stipulated Date of Commencement
January 16 2019
Stipulated Date of Completion /
Likely Date of Completion January 30 2020
Likely Date of Completion January 30 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,461,292.00
Awarded for
₹ 13,923,377.44
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Rahul Constructions
Consultants
M/s. Nitin Arolkar