Project Duration
Stipulated Date of Commencement August 23 2018
Stipulated Date of Completion /
Likely Date of Completion
March 06 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,861,862.00
Awarded for ₹ 6,304,209.00

Project highlights

Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.

 
Gallery Image
Contractors
M/s.Sandeep R S Khandeparkar
Gallery Image
Consultants
M/s.Vaishali Pednekar Associates
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation & maintenance of Government primary SchoolS in State of Goa-Quepem Taluka-GPS Mangal

View Project
Similar Project

Repairs/Upgradation & maintenance of Government schools in the state of Goa – Tiswadi taluka – Package-I (GPS Dhulapi, GPS Mangoda, GPS Gawant, GPS Akhada)

View Project
Similar Project

Construction of Government Primary School at Shantinagar – Pissurlem in Sattari Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.