Project Duration
Stipulated Date of Commencement
September 26 2018
Stipulated Date of Completion /
Likely Date of Completion August 11 2019
Likely Date of Completion August 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 83,21,246.00
Awarded for
₹ 9,319,010.21
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works
Contractors
M/s.Joshi Constructions
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka- Package C (G.P.S Gaokarwada Mayem, G.P.S Shirodawadi Mulgao, G.P.S. Haturli Mayem)
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Pernem Taluka: Package – V (GPS Tiwade Dhargal, GPS Chandel, GPS Madkai Ozari, GPS Varkhand, GPS Bhatpavni, GPS Patradevi, GPS Fakirpata Torse, GPS Tulaskarwadi)
View Project
Repairs/ Up gradation & maintenance of Government schools in the state of Goa- Civil, Plumbing & Electrical works. (Ponda Taluka)-Package-III-G
View Project