Project Duration
Stipulated Date of Commencement November 14 2021
Stipulated Date of Completion /
Likely Date of Completion
January 13 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,061,602.01
Awarded for ₹ 1,156,969.00

Project highlights

Interior work for Panchayat building

 
Gallery Image
Contractors
M/S. Creation Interior Contractors
Gallery Image
Consultants
M/s. Datta Kare Associate
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of Infrastructure in the Rural Areas under Deen Dayal Panchayat Raj Infrastructure Development(Golden Jubilee) Scheme 2013 – Reconstruction of Panchayat Ghar at V.P. Siolim-Sodiem, Siolim, Bardez-Goa

View Project
Similar Project

Construction of Footpath at Old Goa for Exposition 2014

View Project
Similar Project

Refurbishment of ornamental poles along with allied electrical works in the state of Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.