Project Duration
Stipulated Date of Commencement
November 13 2017
Stipulated Date of Completion /
Likely Date of Completion November 12 2018
Likely Date of Completion November 12 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 127,693,445.00
Awarded for
₹ 133,860,915.16
Project highlights
Olympic size Swimming Pool of size 50x25x2m.
Diving Pool of size 18x18x4.5m with RCC diving platforms for heights 1m. 3m. 5m & 7.5m.
Kids Pool of 150M2, Filtration Plant -200 m2.
Contractors
M/s. S.N. Construction
Consultants
M/s TPF Engineering Pvt. Ltd.
(Goa Regional Office)
See Similar Projects
Repairs/Upgradation & Maintenance of Government High School & Primary School – Maina, Quepem, Goa.
View Project
Reconstruction of school at GPS Bicholim (Central)- Erection of 200KVA DTC along with the associated H.T UG Cable
View Project
Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa- (Ponda Taluka) – (GPS Par,Kantar,Tiral,Nanus,Paludi,Dhatwada,& Kassailye Usgao)
View Project





