Project Duration
Stipulated Date of Commencement June 20 2008
Stipulated Date of Completion /
Likely Date of Completion
September 20 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rs.3,63,53,407.64
Awarded for ₹ 52,100,720.15

Project highlights

Swimming pool (25.40 x 20.40 mts.), with depth varying from 1.098 to 1.824 mts. The size of Baby pool is 5.40 x 5.61 mts. Changing rooms for ladies and gents. Shower rooms for ladies and gents, Office,Common room, adequate toilet facilities, Ample parking facilities, Soft landscaping in the premises with illumination.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. M. S. Suctancar
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation & Maintenance of Government Schools in the State of Goa -Civil, Plumbing and Electrical works- Salcete Taluka- Package E (GPS Assolna, GPS Maina Curtorim, GPMS Bhati Curtorim, GPS Telaulim) (2nd call)

View Project
Similar Project

Repairs/ upgradation of GPS at Sanvordem

View Project
Similar Project

Reconstruction of Government Primary School at Arla Querim – Civil, Plumbing and Electrical Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.