Project Duration
Stipulated Date of Commencement
June 20 2008
Stipulated Date of Completion /
Likely Date of Completion September 20 2009
Likely Date of Completion September 20 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rs.3,63,53,407.64
Awarded for
₹ 52,100,720.15
Project highlights
Swimming pool (25.40 x 20.40 mts.), with depth varying from 1.098 to 1.824 mts. The size of Baby pool is 5.40 x 5.61 mts. Changing rooms for ladies and gents. Shower rooms for ladies and gents, Office,Common room, adequate toilet facilities, Ample parking facilities, Soft landscaping in the premises with illumination.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. M. S. Suctancar
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa -Civil, Plumbing and Electrical works- Salcete Taluka- Package E (GPS Assolna, GPS Maina Curtorim, GPMS Bhati Curtorim, GPS Telaulim) (2nd call)
View Project
Repairs/ upgradation of GPS at Sanvordem
View Project
Reconstruction of Government Primary School at Arla Querim – Civil, Plumbing and Electrical Works
View Project