Project Duration
Stipulated Date of Commencement
December 24 2019
Stipulated Date of Completion /
Likely Date of Completion April 05 2021
Likely Date of Completion April 05 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 77,957,826.00
Awarded for
₹ 74,565,448.00
Project highlights
The scope of work involved construction of new bypass road from Ambeudak, Sanvordem to Devnamol in V. P. Kalay and Savordem. The total length of the road is 2.14 km, which comprises of construction of retaining wall, culverts, storm water drain, hot-mixing, etc.
Contractors
M/s. Ritesh Developers
Consultants
M/s. Vijaykumar Sawant, And Associates