Project Duration
Stipulated Date of Commencement February 26 2004
Stipulated Date of Completion /
Likely Date of Completion
August 25 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,611,394.00
Awarded for ₹ 14,350,277.00

Project highlights

• First four lane bridge in Goa.
• The bridge serves as an important link joining the southern part of Goa to the Margao city.
• Length : 18.6 m, width : 19 m including footpaths.
• Length of approaches : 100 m, width : 19 m with adequate lighting and proper drainage system.

 
Gallery Image
Contractors
M/s. Laxmi Civil Engg. Services Pvt. Ltd.
Gallery Image
Consultants
M/s. Keni & D’Souza
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bridge across Baga creek at Baga including approaches.

View Project
Similar Project

Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 11 KV Cable

View Project
Similar Project

Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa. SH: Supply of 20ftX30 ft National Flag

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.