Project Duration
Stipulated Date of Commencement February 27 2014
Stipulated Date of Completion /
Likely Date of Completion
April 27 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,232,612.00
Awarded for ₹ 9,932,510.00

Project highlights

The scope of work involves supply and installation of decorative street light poles on the Service road.

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Construction of Jetty at Brittona – Additional works.

View Project
Similar Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji

View Project
Similar Project

Widening of road in Calangute – Baga – Electrical works..

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.