Project Duration
Stipulated Date of Commencement
January 11 2004
Stipulated Date of Completion /
Likely Date of Completion July 11 2004
Likely Date of Completion July 11 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 44,976,000.00
Awarded for
₹ 37,779,000.00
Project highlights
Upgradation of road from Vodli to Kalay in Sanguem Taluka.
Contractors
M/s. Peter B. Colaco & Sons
Consultants
M/s. S. N. Bhobe & Associates Pvt. Ltd.
See Similar Projects
Widening of roads and relocation of structures in Fatorda Constituency – Phase II – Illumination of Footpath from Colva Circle to Ravindra Bhavan Circle at Fatorda, Margao, Goa
View Project
Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Panjim – HT Cable work from EDC Substation to Chimbel junction – Additional Work
View Project
Acoustic work for Multipurpose Hall.
View Project