Project Duration
Stipulated Date of Commencement
November 29 2017
Stipulated Date of Completion /
Likely Date of Completion December 05 2017
Likely Date of Completion December 05 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 253,495.00
Awarded for
₹ 276,450.00
Project highlights
The scope of work includes supply, installation, testing & commissioning of 11 KV, 3C x 300 sq. mm, underground armored cable – 120 meters length.
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. Rahul Deshpande