Project Duration
Stipulated Date of Commencement
June 25 2016
Stipulated Date of Completion /
Likely Date of Completion October 24 2016
Likely Date of Completion October 24 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 51,806,756.00
Awarded for
₹ 51,703,753.99
Project highlights
Bridge is having two lanes with carriage way of 7.5m and footpath of 2.25m on either side. The Bridge consists of single span of length 24m and having deck slab of 240mm depth
Contractors
M/s.Assmas Constructions Pvt. LTd
Consultants
M/s.Madhav Kamat & Associates