Project Duration
Stipulated Date of Commencement
July 16 2015
Stipulated Date of Completion /
Likely Date of Completion January 15 2016
Likely Date of Completion January 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,607,156.00
Awarded for
₹ 19,080,996.00
Project highlights
Barricading work along St. Creek Boundary
Contractors
M/s. RS Lawande
Consultants
M/s. LKS India Pvt. Ltd.