Project Duration
Stipulated Date of Commencement March 05 2014
Stipulated Date of Completion /
Likely Date of Completion
August 04 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 25,219,798.80
Awarded for ₹ 26,356,358.00

Project highlights

Maintenance of bridges

 
Gallery Image
Contractors
M/s.Goa Friends Engineering & Electrical Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Design and Construction of Grade Separator at Dabolim Airport.

View Project
Similar Project

Widening of road in Calangute – Baga – Electrical works..

View Project
Similar Project

Design and construction of Aldona – Corjuem bridge across river Mapusa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.