Project Duration
Stipulated Date of Commencement May 01 2008
Stipulated Date of Completion /
Likely Date of Completion
January 31 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 25,895,502.00
Awarded for ₹ 38,898,833.00

Project highlights

* Length of the bridge is 62 m.
* Carriageway of the bridge is 7.5 m with 1 m footpath on one side.
*Superstructure consists of RCC deck.
* Bridge comprises of 7 piers and 2 abutments.
* Length of approach roads is 93.50 m in the North and 63.00 m in the South with adequate lighting and proper drainage system.

 
Gallery Image
Contractors
M/s. Aditya Construction Company
Gallery Image
Consultants
M/s. Keni & D’Souza
 
Similar Projects

See Similar Projects

Similar Project

Construction of Pirna Ozrim bridge including approaches.

View Project
Similar Project

Strengthening and Hot Mixing of road from Sanquelim to Karnataka State Border via Keri (Sattari Taluka) from Ch 0.00 to Ch. 26.50 Kms.

View Project
Similar Project

Design and construction of Bridge across River Zuari between Amona and Virdi. SH: Supply of LED Fittings, Poles and Brackets

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.