Project Duration
Stipulated Date of Commencement January 22 2003
Stipulated Date of Completion /
Likely Date of Completion
July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,631,835.00
Awarded for ₹ 29,280,000.00

Project highlights

• Length : 40 m.
• The bridge consists of cast-in-situ continuous R.C.C. T beam superstructure.
• Carriage way 7.5 m wide with kerbs, railings and footpaths on both the sides.
• Approaches on Uguem and Kalay side.
• Electric poles with fixtures on the bridge and approaches.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Additional works from Sai Service Junction to Training College Junction at Porvorim, Goa

View Project
Similar Project

Signages.

View Project
Similar Project

Upgradation of the Road connecting Integrated School Complex to NH17 – Civil, Plumbing & Electrical works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.