Project Duration
Stipulated Date of Commencement
April 28 2016
Stipulated Date of Completion /
Likely Date of Completion July 27 2016
Likely Date of Completion July 27 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rs. 24,77,777.00
Awarded for
₹ 2,477,777.00
Project highlights
Air conditioned outlet for selling Horticulture produce
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Ankit Prabhudessai
See Similar Projects
Balance beautification works from Miramar Circle to Betim Ferry Ramp
View Project
Storm Water Drainage.
View Project
Construction of washrooms at Old Goa for Exposition 2014 – Package I.
View Project