Project Duration
Stipulated Date of Commencement
August 19 2014
Stipulated Date of Completion /
Likely Date of Completion October 02 2014
Likely Date of Completion October 02 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,159,205.60
Awarded for
₹ 1,204,885.57
Project highlights
Additional firefighting works for the project
Contractors
M/s.Psytech Infosolutions (India) Pvt. Ltd.
Consultants
In-house (GSIDC)