Project Duration
Stipulated Date of Commencement April 10 2022
Actual Date of Completion January 25 2024
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,327,021.00
Awarded for ₹ 52,192,413.00

Project highlights

7 mtrs wide pedestrain steel bridge connecting mandovi promenade & DB Road, 2.5 mtrs wide with cycle track & 4.5 mtrs footpath with granite finish

 
Gallery Image
Contractors
M/s. DHIPL Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. LKS India Pvt. Ltd.,
 
Similar Projects

See Similar Projects

Similar Project

Civil & Electrical works

View Details
Similar Project

Design and Construction of Bridge across River Mandovi at Panaji including approaches on NH 17 between Pundalik Nagar Junction (Porvorim) and Merces Junction

View Details
Similar Project

Widening of roads and relocation of structures in Fatorda Constituency- Phase I

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.