Status
Completed
Contractors
Consultants
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of building at Patto with provision for Gas Insulated Sub Station, Panaji, Goa Phase I – Electrical Works
Completed
Project Duration
Stipulated Date of Commencement
December 04 2021
Actual Date of Completion
July 31 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,212,628.80
Awarded for
₹ 1,249,999.00
Project highlights
Electrification of Gas Insulated Sub Station Building
Contractors
M/s.Volton Engineering India Private Limited
Consultants
M/s. Vijaykumar Sawant & Associates
See Similar Projects
Construction of compound wall for Biomedical waste treatement facility at Kundaim.
View Details
Construction of two number of sheds for treatment of dry waste within the Corporation of the City of Panaji (CCP) jurisdiction – Electrical works at St. Inez.
View Details
Reconstruction/Repair of Excise Outpost Kiranpani, Paliem, Pernem, Goa
View Details