Status
Completed
Contractors
Consultants
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of building at Patto with provision for Gas Insulated Sub Station, Panaji, Goa Phase I – Electrical Works
Completed
Project Duration
Stipulated Date of Commencement
December 04 2021
Actual Date of Completion
July 31 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,212,628.80
Awarded for
₹ 1,249,999.00
Project highlights
Electrification of Gas Insulated Sub Station Building
Contractors
M/s.Volton Engineering India Private Limited
Consultants
M/s. Vijaykumar Sawant & Associates