Project Duration
Stipulated Date of Commencement October 08 2016
Actual Date of Completion June 15 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,388,910.00
Awarded for ₹ 8,326,480.10

Project highlights

The scope of work includes Renovation of the existing police outpost.

 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s. Nitin Arolkar
 