Project Duration
Stipulated Date of Commencement July 26 2016
Actual Date of Completion March 01 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 999,534.00
Awarded for ₹ 1,044,450.00

Project highlights

The scope of work includes supply, installation, testing & commissioning of :
a) 160kVA,11/.415kV Distribution transformer
b) 11kV Load Break Switch
c) HT Metering cubicle and other allied electrical works.

 
Gallery Image
Contractors
M/s. Aditya Electromech Services
Gallery Image
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Readymade Furniture work

View Details
Similar Project

Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil,Plumbing & Electrical works – Package B (Mormugao Taluka) GPMS Curpawada, GPMS Jetty.

View Details
Similar Project

Extension / Upgradation of Government College of Arts, Science & Commerce at Khandola, Marcel, Goa

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.