Project Duration
Stipulated Date of Commencement
July 26 2016
Actual Date of Completion
March 01 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 999,534.00
Awarded for
₹ 1,044,450.00
Project highlights
The scope of work includes supply, installation, testing & commissioning of :
a) 160kVA,11/.415kV Distribution transformer
b) 11kV Load Break Switch
c) HT Metering cubicle and other allied electrical works.
Contractors
M/s. Aditya Electromech Services
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.