Project Duration
Stipulated Date of Commencement July 26 2016
Actual Date of Completion March 01 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 999,534.00
Awarded for ₹ 1,044,450.00

Project highlights

The scope of work includes supply, installation, testing & commissioning of :
a) 160kVA,11/.415kV Distribution transformer
b) 11kV Load Break Switch
c) HT Metering cubicle and other allied electrical works.

 
Gallery Image
Contractors
M/s. Aditya Electromech Services
Gallery Image
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Upgradation/Renovation of Government College at Quepem, Goa -Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.

View Details
Similar Project

Development of Government Village School Playground at Assonora in Bardez taluka (Assonora Sports Complex)

View Details
Similar Project

Construction of Government Primary School at Shantinagar – Pissurlem in Sattari Taluka.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.