Project Duration
Stipulated Date of Commencement
May 04 2010
Actual Date of Completion
January 03 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,863,898.00
Awarded for
₹ 32,438,263.70
Project highlights
Beautification work by providing pavers for footpaths and hotmixing of certain internal roads in Canacona town.
Contractors
M/s. Ritesh Developers Pvt. Ltd.
Consultants
In-house (GSIDC)