Project Duration
Stipulated Date of Commencement July 08 2008
Actual Date of Completion January 07 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 149,211,856.00
Awarded for ₹ 191,699,335.00

Project highlights

Road widening and hotmixing of internal and main roads, construction of drains with precast RCC covers, Footpath with pavers etc. Constructio of seating on foopath along the main road. Renovation of Muncipality Office, construction of compound walls etc.

 
Gallery Image
Contractors
M/s. H. P. Madhukar,
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates
 

Sub Works

This project involved 2 sub works. The details of the same available below

1

Illumination of main road from Forest Guest House to Police Quarters

100% Completed
 
Project Duration
Stipulated Date of Commencement July 03 2010
Actual Date of Completion July 29 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,268,800.00
Awarded for ₹ 2,741,000.00
 
Contractors
Contractors
M/s. James Electrical
Consultants
Consultants
M/s. Vijaykumar Sawant Associates
2

Specialized hand painted tile cladding work

100% Completed
 
Project Duration
Stipulated Date of Commencement June 16 2011
Actual Date of Completion October 15 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,817,618.00
Awarded for ₹ 4,797,750.00

Project highlights

Providing and fixing of hand painted tiles cladding for the seating provided on the Main road.

 
Contractors
Contractors
M/s. Shilpi Constructions
Consultants
Consultants
M/s. Vijaykumar Sawant Associates
Similar Projects

See Similar Projects

Similar Project

Stage lighting

View Details
Similar Project

Electrical Work

View Details
Similar Project

Fire Alarm.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.