Project Duration
Stipulated Date of Commencement January 28 2013
Actual Date of Completion February 28 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,00,41,753.00
Awarded for ₹ 3,90,22,573.00
 
Gallery Image
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 

Sub Works

This project involved 2 sub works. The details of the same available below

1

Electrical Works.

100% Completed
 
Project Duration
Stipulated Date of Commencement May 26 2013
Actual Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 23,50,771.00
Awarded for ₹ 23,88,737.00
 
Contractors
Contractors
M/s. Mohan Electricals
Consultants
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
2

HVAC Works.

100% Completed
 
Project Duration
Stipulated Date of Commencement September 26 2013
Actual Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,324,109.94
Awarded for ₹ 5,899,999.00
 
Contractors
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
Similar Projects

See Similar Projects

Similar Project

Steel Operation Theatre work.

View Details
Similar Project

Renovations of old IPHB Building to accommodate Goa Commission for Backward Classes, Nursing Hostel and College and Directorate of Food & Drugs.

View Details
Similar Project

Interior works – Phase II.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.