Project Duration
Stipulated Date of Commencement June 22 2021
Actual Date of Completion May 15 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 32,467,692.26
Awarded for ₹ 29,549,827.65

Project highlights

The project involves upgradation of new NICU ward above ward 123 at GMC, which provides high dependency area , ventilator room, isolation room, mini OT, Preparation room etc.

 
Gallery Image
Contractors
M/s. Virender Kumar & Co.,
Gallery Image
Consultants
M/s. Frischmann Prabhu I Pvt. Ltd.
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Upgradation of NICU at Goa Medical College, Bambolim at Goa-Supply, Installation, Testing and Commissioning of DG Set.

100% Completed
 
Project Duration
Stipulated Date of Commencement June 19 2024
Actual Date of Completion
Status
0%
Completed
Cost (₹)
Estimated at ₹ 4,317,391.53
Awarded for ₹ 4,520,748.60

Project highlights

Supply, Installation, Testing and Commissioning of DG Set.

 
Contractors
Contractors
M/s. Imperial Engineering Company
Consultants
Consultants
M/s. FP Project Management
Similar Projects

See Similar Projects

Similar Project

Face-lift to Tisk Usgao Hospital building including staff quarters

View Details
Similar Project

External electrical works at area around new Library Building and Power supply to new Library building at GMC Complex.

View Details
Similar Project

Reconstruction / Upgradation of Primary Health Centre at Sanquelim, Goa -Civil & Plumbing work.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.