Project Duration
Stipulated Date of Commencement
June 22 2021
Actual Date of Completion
May 15 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 32,467,692.26
Awarded for
₹ 29,549,827.65
Project highlights
The project involves upgradation of new NICU ward above ward 123 at GMC, which provides high dependency area , ventilator room, isolation room, mini OT, Preparation room etc.
Contractors
M/s. Virender Kumar & Co.,
Consultants
M/s. Frischmann Prabhu I Pvt. Ltd.
Sub Works
This project involved 1 sub works. The details of the same available below
1
Upgradation of NICU at Goa Medical College, Bambolim at Goa-Supply, Installation, Testing and Commissioning of DG Set.
100% Completed
Project Duration
Stipulated Date of Commencement
June 19 2024
Actual Date of Completion
Status
0%
Completed
Cost (₹)
Estimated at
₹ 4,317,391.53
Awarded for
₹ 4,520,748.60
Project highlights
Supply, Installation, Testing and Commissioning of DG Set.
Contractors
M/s. Imperial Engineering Company
Consultants
M/s. FP Project Management
See Similar Projects
Medical gas and Vacuum System work
View Details
Upgradation and extension of existing Cottage Hospital at Chicalim, Goa – (120 Bedded Cottage Hospital, Chicalim) Civil, Plumbing, Electrical, Firefighting, HVAC, Lifts and Land development works
View Details
Construction of compound wall for the Goa Medical College, Hospital at Bambolim, Goa.
View Details