Project Duration
Stipulated Date of Commencement
January 17 2014
Actual Date of Completion
February 13 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 975,000.00
Awarded for
₹ 970,000.00
Contractors
M/S. ENCARTA PHARMA PVT. LTD
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.