Project Duration
Stipulated Date of Commencement
December 22 2013
Actual Date of Completion
February 14 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,739,427.00
Awarded for
₹ 8,381,689.88
Contractors
M/s. OVERSEAS ASSOCIATES
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.