Project Duration
Stipulated Date of Commencement June 16 2006
Actual Date of Completion August 30 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 45,331,777.00
Awarded for ₹ 43,374,376.00

Project highlights

Power upgradation work includes utility buiding, 33 KV substation, HT panels, LT panels and 11 KV ring main unit (RMU) and cabling.

 
Gallery Image
Contractors
M/s. ABB Ltd.
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa S.H.: Supply, Installation, Testing & Commissioning of 500KVA DG set at North Goa District Hospital, Mapusa

View Details
Similar Project

Supply, Installation, Testing and Commissioning of Cardiac output Monitoring System

View Details
Similar Project

Supply, Testing and Commissioning of Anaesthesia Workstation

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.