Project Duration
Stipulated Date of Commencement June 16 2006
Actual Date of Completion August 30 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 45,331,777.00
Awarded for ₹ 43,374,376.00

Project highlights

Power upgradation work includes utility buiding, 33 KV substation, HT panels, LT panels and 11 KV ring main unit (RMU) and cabling.

 
Gallery Image
Contractors
M/s. ABB Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Maintenance/Renovation works of Community Health Centre at Valpoi S.H.- Maintenance of Air Conditioners

View Details
Similar Project

Maintenance contract for 8 Nos. of elevators installed at North Goa District Hospital Mapusa for 3 years

View Details
Similar Project

Restoration and Adaptive re-use of Old GMC.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.