Project Duration
Stipulated Date of Commencement September 19 2020
Actual Date of Completion October 31 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 132,746,096.00
Awarded for ₹ 131,078,400.10

Project highlights

The project consist of: Recreation of Rooms, Vocational activity rooms, Computer lab, Library, Group Therapy. It also consists of Yoga Rooms, a Recreational Room and muiltiple activity rooms

 
Gallery Image
Contractors
M/s.Tirupati Sarjan Limited
Gallery Image
Consultants
M/s. Pankaj Joshi Consultant (to be foreclosed) M/s.FPPM is being appointed.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Yatri Niwas at GMC Complex, Bambolim, Goa -Civil, Plumbing & Internal Electrical works

View Details
Similar Project

Supply Installation Testing & Commissioning of water Heater & Purifier

View Details
Similar Project

Restoration and Adaptive re-use of Old GMC.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.