Status
Completed
Contractors
Consultants
Sub Works
This project involved 2 sub works. The details of the same available below
1
Renovations of old IPHB Building to accommodate Goa Commission for Backward Classes
Completed
Project Duration
Stipulated Date of Commencement
September 08 2004
Actual Date of Completion
October 08 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 350,184.40
Awarded for
₹ 366,922.00
Contractors
M/s. Sandesh C. Naik
Consultants
M/s. Vijaykumar Sawant Associates
2
Renovations of old IPHB Building to accommodate Nursing Hostel and College and Directorate of Food & Drugs
Completed
Project Duration
Stipulated Date of Commencement
February 27 2004
Actual Date of Completion
December 26 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 39.85 lakh
Awarded for
₹ 39.81 lakh
Contractors
M/s. Sandesh C. Naik and M/s. C. V. Naik & Son
Consultants
M/s. Vijaykumar Sawant Associates