Project Duration
Stipulated Date of Commencement
November 06 2009
Actual Date of Completion
July 15 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,926,785.00
Awarded for
₹ 5,308,124.00
Project highlights
Electrical works
Contractors
M/s. Sunshine Electric Co. Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd