Project Duration
Stipulated Date of Commencement June 23 2015
Actual Date of Completion September 22 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,066,421.00
Awarded for ₹ 4,545,045.00

Project highlights

Air conditioning work

 
Gallery Image
Contractors
M/s. Speedfrost Services Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Furniture / Interior works.

View Details
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – S.H- Maintenance /Renovation work of Community Health Center at Canacona – Maintenance Contract for Schindler Elevator installed at Canacona CHC

View Details
Similar Project

Construction of District Hospital at Mapusa, Goa

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.