Project Duration
Stipulated Date of Commencement
December 14 2012
Actual Date of Completion
January 20 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 823,021.00
Awarded for
₹ 926,207.80
Project highlights
Compound wall
Contractors
M/s. Sandeep R. S. Khandeparkar
Consultants
In-house (GSIDC)