Project Duration
Stipulated Date of Commencement
August 19 2019
Actual Date of Completion
August 18 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 143,603.89
Awarded for
₹ 143,603.89
Project highlights
AMC for 200kVA Transformer
Contractors
M/s. L.R. Enterprises
Consultants
In-house (GSIDC)