Project Duration
Stipulated Date of Commencement
January 27 2004
Actual Date of Completion
January 26 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 47,466,000.00
Awarded for
₹ 45,103,376.00
Contractors
M/s. Gannon Dunkerley & Co. Ltd.
Consultants
M/s. Madhav Kamat & Associates
Sub Works
This project involved 5 sub works. The details of the same available below
1
Interior Works
100% Completed
Project Duration
Stipulated Date of Commencement
December 30 2005
Actual Date of Completion
May 13 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,998,478.00
Awarded for
₹ 2,123,561.34
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Madhav Kamat & Associates
2
Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators
100% Completed
Project Duration
Stipulated Date of Commencement
December 30 2005
Actual Date of Completion
September 06 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,970,000.00
Awarded for
₹ 1,793,000.00
Contractors
M/s. Schindler (I) Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
3
Supply, installation, testing and commissioning of transformer yard and diesel generating set.
100% Completed
Project Duration
Stipulated Date of Commencement
June 15 2006
Actual Date of Completion
September 14 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,919,050.00
Awarded for
₹ 3,119,950.00
Contractors
M/s. G. V. Electricals
Consultants
M/s. Madhav Kamat & Associates
4
Construction of Sewage Treatment Plant and Elevated tank platform.
100% Completed
Project Duration
Stipulated Date of Commencement
July 23 2006
Actual Date of Completion
April 15 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,144,443.00
Awarded for
₹ 1,210,535.00
Contractors
M/s. Chowgule Industries (I) Ltd.
Consultants
M/s. Madhav Kamat & Associates
5
Supply, installation, testing and commissioning of Air Conditioners and ventilation system
100% Completed
Project Duration
Stipulated Date of Commencement
September 10 2006
Actual Date of Completion
May 20 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,247,890.00
Awarded for
₹ 1,654,105.00
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Renovation/Maintenance of Hospitals CHC’s, PHC’s, RMD’s under Directorate of Health Services in South Goa- S.H.- Renovation/Maintenance work of primary Health Centre at Shiroda – Annual Maintenance contract of 320 KVA DG Set for Three years.
View Details
Maintenance works of Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa. SH – Carriage of water”
View Details
Maintenance contract for 8 Nos. of elevators installed at North Goa District Hospital Mapusa for 3 years
View Details