Project Duration
Stipulated Date of Commencement
June 24 2022
Actual Date of Completion
February 15 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,066,766.80
Awarded for
₹ 13,903,408.51
Project highlights
Additional internal and external works in the new CHC premises
Contractors
M/s. Sri Srinath Infra
Consultants
M/s. Saolapurkar and Associates