This project involved 6 sub works. The details of the same available below

1

Construction of Anganwadi Centres from NABARD Assistance – Package II (GPS Sangao Ozari, GPS Sakral Torse).

100% Completed
 
Project Duration
Stipulated Date of Commencement May 25 2011
Actual Date of Completion August 30 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,882,049.00
Awarded for ₹ 4157111.35
 
Contractors
Contractors
M/s. Rakesh Bandekar,
Consultants
Consultants
M/s. Datta Kare Associates
2

Construction of Anganwadi Centres from NABARD Assistance – Package III (GPS Pernem, GPS Mandrem, GPS Korgao).

100% Completed
 
Project Duration
Stipulated Date of Commencement December 29 2011
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,526,892.00
Awarded for ₹ 7179487.8
 
Contractors
Contractors
M/s. Ask Developers
Consultants
Consultants
M/s. Datta Kare Associates
3

Construction of Anganwadi Centres from NABARD Assistance – Package IV (GPS Chandel, GPS Ibrampur, GPS Hansapur).

100% Completed
 
Project Duration
Stipulated Date of Commencement May 05 2011
Actual Date of Completion September 30 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,683,732.52
Awarded for ₹ 6086790.88
 
Contractors
Contractors
M/s. M. M. Naik & Co.
Consultants
Consultants
M/s. Datta Kare Associates
4

Construction of Anganwadi Centres from NABARD Assistance – Package V (GPS Kajrechi Vhali, GPS Dhangarwada Bhuipal, GPS Ghoteli No.1)

100% Completed
 
Project Duration
Stipulated Date of Commencement December 28 2010
Actual Date of Completion December 31 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,166,556.00
Awarded for ₹ 6632510.73
 
Contractors
Contractors
M/s. M. M. Naik & Co.
Consultants
Consultants
M/s. Datta Kare Associates
5

Construction of Anganwadi Centres from NABARD Assistance – Package VI (GPS Betmoddi Kakoda, GPS Bendurdem, GPS Cumbeabhat Velim).

100% Completed
 
Project Duration
Stipulated Date of Commencement September 22 2011
Actual Date of Completion February 28 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,062,925.00
Awarded for ₹ 6669089.99

Project highlights

Construction of Anganwadi Centres

 
Contractors
Contractors
M/s. Ask Developers
Consultants
Consultants
M/s. Datta Kare Associates
6

Construction of Anganwadi Centres from NABARD Assistance – Package VII (GPS Bethoda).

100% Completed
 
Project Duration
Stipulated Date of Commencement October 17 2011
Actual Date of Completion August 15 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,834,743.14
Awarded for ₹ 2006449.53
 
Contractors
Contractors
M/s. Ask Developers
Consultants
Consultants
M/s. Datta Kare Associates
Similar Projects

See Similar Projects

Similar Project

Furnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Details
Similar Project

Extension of H. B. Government High School at Thane in Sattari Taluka.

View Details
Similar Project

Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka –Sanguem taluka -Package I- (GPS Dando, GPS Dapode, GPS Kongare, GPS Kotharli, GPS Valkini Colony no. 3)

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.