Project Duration
Stipulated Date of Commencement
June 14 2013
Actual Date of Completion
February 28 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,056,644.00
Awarded for
₹ 10,977,261.50
Project highlights
Lab furniture work
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Banaji & Associates