Project Duration
Stipulated Date of Commencement
May 11 2016
Actual Date of Completion
May 30 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,917,386.00
Awarded for
₹ 11,661,561.16
Project highlights
Repairs/ upgradation of schools which include proviison of new double skin galvalum sheet roofing, tiling, painting etc.
Contractors
M/s.K.G Thomas
Consultants
M/s.Nitin Arolkar