Project Duration
Stipulated Date of Commencement
August 03 2018
Actual Date of Completion
July 28 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,252,849.00
Awarded for
₹ 8,610,526.17
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Bharti Infrastructure Developers
Consultants
M/s.Nitin Arolkar
See Similar Projects
Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-D
View Details
Repairs/upgradation & maintenance of Govt. schools in the State of Goa – Sattari Taluka: Package D- GPS Brahmkarmali, GPS Dhave, GPS Kankire, GHS Nagargao, GPS Charvane, GPS Varshe, GHS Dhabem
View Details
Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-C
View Details