Project Duration
Stipulated Date of Commencement
October 28 2016
Actual Date of Completion
September 30 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,721,364.00
Awarded for
₹ 11,039,275.00
Project highlights
Repair & upgradation work of the school building, including roofing, painting, tilling, plumbing work etc
Contractors
M/s. Sirrajuddin Beig
Consultants
M/s. Nitin Arolkar