Project Duration
Stipulated Date of Commencement
July 19 2018
Actual Date of Completion
February 15 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 66,81,190.25
Awarded for
₹ 7,087,775.45
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.ASK Developers
Consultants
M/s. Datta Kare Associates