Project Duration
Stipulated Date of Commencement
August 03 2018
Actual Date of Completion
July 28 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,252,849.00
Awarded for
₹ 8,610,526.17
Final Cost of Project
₹ 5,289,192.91
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s Bharti Infrastructure Developers
Consultants
M/s Nitin Arolkar