Project Duration
Stipulated Date of Commencement
November 01 2017
Actual Date of Completion
May 14 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,00,000.00
Awarded for
₹ 5,843,796.96
Project highlights
Repairs/Upgradation & maintenance of Government schools in the state of Goa- Civil, Plumbing & Electrical works
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates