Project Duration
Stipulated Date of Commencement
January 03 2019
Actual Date of Completion
March 31 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,663,483.00
Awarded for
₹ 9,524,113.18
Contractors
M/s. A. Y. Gulumkar
Consultants
M/s. Oracle structural consultant