Project Duration
Stipulated Date of Commencement
March 03 2023
Stipulated Date of Completion /
Likely Date of Completion October 02 2023
Likely Date of Completion October 02 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,825,534.00
Awarded for
₹ 8,405,989.77
Project highlights
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa
Contractors
M/s. Rakesh Kambli
Consultants
M/s. Bhasker Wagle & Associates