Project Duration
Stipulated Date of Commencement
March 27 2007
Actual Date of Completion
February 23 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 54,371,959.00
Awarded for
₹ 69,139,000.00
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of Swimming pool at Ponda Sports Complex – Additional works such as Jogging Track, Road, Compound wall, Security Cabin etc.
100% Completed
Project Duration
Stipulated Date of Commencement
February 12 2009
Actual Date of Completion
June 07 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,71,379.00
Awarded for
₹ 47,00,750.52
Contractors
M/s. Rohit Equipments
Consultants
M/s. Datta Kare Associates
See Similar Projects
Construction of Higher Secondary School building for Dr.K.B.Hedgewar Higher Secondary School at Cujira, Bambolim,Tiswadi,Goa.
View Details
Reconstruction of school at GPS Bicholim (Central) – Additional Work
View Details
Repairs, Upgradation & Maintenance of Government Schools in the State of Goa – Packge O (Sattari Taluka) – (GPS, Gaonkarwada Vantem, GPS Vantem, GPS Advoi)
View Details