Project Duration
Stipulated Date of Commencement October 05 2006
Actual Date of Completion January 15 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 64,52.615.88
Awarded for ₹ 7,217,000.00

Project highlights

The work included supply and fixing of paver blocks, kerbs, ballusters, granite bollards, etc.

 
Gallery Image
Contractors
M/s. Madanant Constructions (Goa) Pvt. Ltd.
Gallery Image
Consultants
M/s. Construma Consultancy Pvt. Ltd.
 